Mayfield Rd. Construction Update PDF Print E-mail
CURRENT ALERTS
 
mayfieldcontructionf.jpg mayfieldcontructione.jpg mayfieldcontructiond.jpg

Section 1 - MAYFIELD RD, LANDER RD EAST TO GOLDEN GATE (south side): One lane in each direction is maintained on the south side of Mayfield Road as crews work on the north side. Work in this section is expected to be completed by mid-August 2008, weather permitting.
 
Section 2 - GOLDEN GATE PLAZA TO WALMART: Work takes place on the south side of Mayfield Road with two lanes in each direction maintained on the north side. During the coming weeks and months, expect shifted ramp configurations at the I-271 interchange.
 
Section 3 - WALMART DRIVE TO THE EAST CORPORATION LIMIT: This section is completely open to traffic. Only minor operations remain.
 
Access to all Mayfield Road businesses is being maintained. Alternate routes to all business are available and easily accessible.
 


 
Last Updated ( Thursday, 31 July 2008 )